The Army issued a request for proposals for Enhanced Use Leases at nine military installations nationwide on Nov. 20. Proposals are due Jan. 18, 2027, under an initial 25-year lease term.
No data center has been authorized at any of the nine sites. The solicitation opens a competitive leasing process, and any project would require further evaluation, selection, and approvals.
Power Generation Is the Primary Ask
Data centers are a preferred addition to power-generation projects, not a standalone requirement.
The Army is seeking commercial power-generation facilities first. Integrated data centers are preferred but not mandatory, and data-center-only proposals will not be considered.
The nine installations are Joint Base Lewis-McChord in Washington, Fort Bragg in North Carolina, Fort Hood in Texas, Fort McCoy in Wisconsin, and Fort Rucker in Alabama. The list also includes Blue Grass Army Depot in Kentucky, Pine Bluff Arsenal in Arkansas, Tooele Army Depot in Utah, and Sierra Army Depot in California.
Energy Resilience Is Embedded in the Requirements
The Army wants backup power operational within one hour and sustained for two full weeks.
Proposed projects must supply backup electricity within one hour of a grid outage. That power must be sustained for at least 14 continuous days.
Water use must meet a net-neutral or better standard, according to the solicitation. That requirement could make local watershed accounting a central factor in how proposals are evaluated.
This Extends an Existing Pattern
Two earlier conditional selections at other installations preceded this broader solicitation.
The Army had previously conditionally selected Carlyle for roughly 1,384 acres at Fort Bliss, Texas. CyrusOne was conditionally selected for roughly 1,201 acres at Dugway Proving Ground, Utah, though neither lease had been finalized at the time of reporting.
A July 2025 executive order directed the defense secretary to competitively lease available military land for data-center development. The nine-installation solicitation broadens that effort.
A Veterans Group Is Asking for a Pause, but on Different Land
Veterans for Public Lands launched on Veterans Day with a request aimed at Interior and Agriculture, not the Pentagon.
Retired Army Lt. Gen. Jeffrey Buchanan chairs Veterans for Public Lands. He commanded U.S. Army North, served four tours in Iraq, and retired from the Army in 2019.
The group launched Nov. 11 and called on the Interior secretary to pause new data-center development on federal public lands. The request asks the government to establish procedures for public participation, environmental review, water and energy safeguards, and tribal consultation.
A separate coalition of 115 organizations sent a parallel letter to Interior Secretary Doug Burgum and Agriculture Secretary Brooke Rollins requesting a moratorium on new commercial data-center authorizations on public lands. The veterans group also urged the incoming Congress to consider moratorium legislation within its first 100 days.
The Two Efforts Are on Separate Legal Tracks
Jurisdiction determines whether any moratorium could reach military property.
The Army operates under Defense Department leasing authorities. The veterans group directed its request at lands managed by Interior and Agriculture; Sen. Ron Wyden's moratorium legislation targets Interior-managed and National Forest land, which does not include military installations.
Sen. Ruben Gallego submitted a separate amendment that would prohibit new privately operated data centers on military installations, with exceptions for facilities serving national-security purposes. That amendment was ordered to lie on the table and had not received a vote.
The Senate passed the Bipartisan American Affordability and Jobs Act 62-33 on Nov. 19 without voting on Wyden's proposal. The Interior Board of Land Appeals separately put a Bureau of Land Management data-center approval near Boulder City, Nevada, on hold Sept. 1.
Key Questions Remain Open
The scope of the veterans group's proposed pause on military land has not been publicly clarified.
Veterans for Public Lands had not publicly stated, in materials reviewed, whether its proposed pause extends to military installations. Military.com reported that the Army, the Interior Department, and Buchanan did not respond to comment requests.
No lease at any of the nine installations has been awarded. The next concrete milestone is the Jan. 18, 2027 proposal deadline, after which the Army will evaluate submissions before any lease selection can proceed.