Contractors in the Kyiv region have been paid UAH824mn in advances, but certificates cover only 2.79% of it, a parliamentary probe found.

Almost all 26 contracts went to three companies without open tenders; one firm is also the designer of every site.

The unfinished sites are being handed to the State Agency for Restoration, which says completion could take up to four months.

Ukraine has put second-level shelters over 235 transformers nationally, and only one protected unit has been hit in six months.

____________________

Ukraine has failed to finish a single one of the 26 shelters meant to shield the Kyiv region's power substations from Russian drones, as winter strikes on the grid intensify and the first snow falls.

'It's complete chaos,' former Ukrenergo chief executive Volodymyr Kudrytskyi said of the programme in an interview with Radio NV, published by NV on November 24. Protection for regional energy facilities, water utilities and gas infrastructure only began to be built at the end of 2025, he said; contractors worked without contracts, 'on their word of honour', and the UAH47bn ($1.04bn) allocated is not enough. No one in the state is responsible for the regions' 'resilience plans', which have remained 'PR on paper'.

The failure matters because Russia is again trying to freeze Ukraine into submission. It has carried out more than 350 attacks on the energy system since September and damaged more than 800 pieces of equipment, Energy Minister Denys Shmyhal told parliament on October 30. The concrete-and-steel 'second level' shelters built over transformers are the one defence that has worked: 235 transformers now have them, and only one protected unit had been hit, by a ballistic missile, in the previous six months, Shmyhal said.

Advances without work

The Kyiv region's programme covered transformers at 26 substations of 110 kV. A parliamentary temporary investigative commission headed by MP Lesia Zaburanna checked the payment records against an engineering inspection of the sites and found that contractors had been paid UAH824mn ($18.2mn) in advances, mostly from the government's reserve fund. Only UAH23mn ($508,000) of that, or 2.79%, had been covered by acceptance certificates for completed work, she said on November 16, Interfax-Ukraine reported.

About UAH801mn ($17.7mn) of advances is unmatched by any certificate. 'This is not the same as established losses, but it requires an immediate check of the actual use of funds, the volume of work done and the materials delivered,' Zaburanna said. The estimated cost of the 26 contracts rose from UAH1.84bn ($40.6mn) to UAH2.28bn ($50.3mn) after adjustment.

The contracts were signed directly, without open tenders on the Prozorro procurement system, and almost all went to three companies. Consulting-Bud holds 14 worth UAH926.85mn ($20.4mn) and has had UAH439.85mn ($9.7mn) in advances, of which UAH15.48mn ($342,000) is covered by certificates. A second firm, UBK Yu.Bi.Si., holds nine contracts and is also the general designer for all 26 sites, a combination Zaburanna said needs checking for a conflict of interest. One smaller contractor, Easy Group, had taken a site to a declared 56% readiness without any advance at all.

The regional administration puts average readiness at 53-55%. Zaburanna's engineers argue the figure means little: a shelter protects a transformer only once its concrete, ventilation and fire systems work as one sealed structure, and a half-built one protects nothing.

Blame moves up the line

Mykola Kalashnyk, who ran the Kyiv regional military administration until July and is now minister for restoration, infrastructure and transport, has said he answers for the decisions taken on his watch. Construction readiness was 40.02% when he left on July 16, he told journalists on November 14, and crept up by about 0.6 percentage points a week until early October, Ukrinform reported.

The contracts were signed by the administration's regional development department under a government experimental scheme that allowed direct awards for protecting critical infrastructure, and were overseen by his then deputy, Ruslan Oliinyk, Kalashnyk said. The administration paid UAH911.44mn ($20.1mn) in advances in all. On October 13 it asked to hand the unfinished sites to the State Agency for Restoration and Infrastructure Development, which will pick new contractors after an audit by the State Audit Service.

The agency's head, Ivan Fedorov, says it is ready to finish them. The ministry has signed off the transfer and the agency is waiting for the regional administration's paperwork, followed by an audit, new contractors and construction, which could take from three weeks to four months depending on the site, he wrote on social media. An audit of the agency's own regional services over two and a half months had found 'unrealistic construction schedules' and no single system of control, Fedorov wrote, and every site is now monitored digitally.

Building for next winter

Fedorov's timetable means some sites around Kyiv will not be protected until well into the heating season. A full cycle of building protection at an energy facility takes six to eight months, he wrote, so decisions for the winter of 2027-2028 have to be taken now. In the capital the agency is building six backup heating plants near the Darnytsia combined heat and power station, aiming to be able to supply backup heat to 80% of buildings by the end of the year.

The money is not the only problem, but it is short. The 2026 budget set aside UAH67.6bn ($1.49bn) for the regions' resilience plans, and about UAH60bn ($1.32bn) more is needed to finish the work already started and build the next round of protection, Ukrinform reported.

The city of Kyiv has fared little better than the region. President Volodymyr Zelenskiy said in October that the capital trailed every other region in carrying out its resilience plan and threatened a shake-up of how it is run, while Mayor Vitali Klitschko blamed limited time, money and manpower. The first big raid of the season, on September 30, damaged the Trypilska power plant, the largest serving the capital region.

Kudrytskyi has a stake in the argument. He was dismissed as head of the grid operator in September 2024 amid reports that the military command was unhappy with the pace of protection work at Ukrenergo's sites, which he denied, pointing to more than 60 anti-drone shelters built at its substations. He was later charged with fraud over a 2018 contract to rebuild substation fencing. The shelters he describes as missing are the regional, lower-voltage layer beneath the 750kV substations that carry the grid's backbone, and that layer, around Kyiv at least, is still a building site.

Source: yahoo.com